Audit Finds U.S. DOT Transit Record-Keeping “Unreliable,” “Inaccurate”

The disjointed state of "New Starts," the Federal Transit Administration's (FTA) program to fund new rail and bus lines, is well-known on Capitol Hill -- in fact, House transportation committee chairman Jim Oberstar (D-MN) recently quipped that it ought to be renamed "small starts, low starts, and no starts."

charlotterail.jpgThousands gathered to board the new light rail line in Charlotte, NC in 2007. Photo via Light Rail Now

With Oberstar's six-year transportation re-write bill in limbo for the moment, however, there appears to be scant political urgency to fix the program. But a report released today by the non-partisan Government Accountability Office (GAO) could help change that picture.

It can take as long as 14 years for transit planners to secure a full-funding New Starts grant agreement (FFGA), the final stage required before starting construction. Yet when GAO auditors set out to break the process down by its stages (which are depicted in a comically complex chart after the jump) they found the FTA could only provide complete information for nine out of 40 New Starts projects approved since 1997.

"We were unable to obtain complete and reliable project milestone data from FTA," GAO auditors wrote. An attempt to confirm records for a random sample of 10 New Starts projects found the information to be "unreliable and, in some cases, inaccurate."

The GAO report then outlined the FTA's explanation for its inconsistent data:

First, FTA told us that it does not have records on when a project begins alternatives analysis because this phase is conducted at the local level, generally without FTA involvement. Second, FTA told us that it does not record when a project sponsor submits an application for preliminary engineering, final design, and FFGA because project sponsors almost never submit complete applications.

The bureaucratic hurdles that transit planners must clear to win federal aid stand in stark contrast to road projects' usually unobstructed path to approval. But without solid data to make the case for fixing New Starts, transit advocates' already arduous political fight for fairer treatment is likely to get even harder.

The GAO report can be downloaded in full here.

d09784_0009.jpgSource: GAO

Stay in touch

Sign up for our free newsletter

More from Streetsblog New York City

Monday’s Headlines: South Williamsburg Edition

Satmar Hasidic leader Moishe Indig endorsed Zohran Mamdani — but didn't demand any anti-bike lane promises from the mayoral frontrunner, he said.

November 3, 2025

NYPD Criminal Bike Crackdown Continues Even as Mamdani Makes Overtures to Tisch

Street safety advocates should not be pleased by Zohran Mamdani's decision to invite NYPD Commissioner Jessica Tisch to stay on. Here's why.

November 3, 2025

City Council Majority Backs Bill to Force Amazon to Hire Its Delivery Workers

Thirty-four City Council members from across the political spectrum want to force Amazon to directly employ and better train its delivery workers.

November 3, 2025

Spooky Stuff: On Halloween, Some Places Have Deadlier Roads Than Others

New York City hasn't proven to be that scary on the candy-filled holiday. But it's still a bad idea to mix kids, darkness and cars.

October 31, 2025

Friday’s Headlines: After the Flood Edition

Flooding that would happen once in a while now happens a few times a year. Plus other news.

October 31, 2025

Amtrak’s Penn Station Plans Assume Gateway Tunnel Will Happen Despite Trump ‘Termination’

Andy Byford's Penn Station plans assume a capacity boost from the Gateway Tunnel project that President Trump insists is "terminated."

October 30, 2025
See all posts