What D.C. Metro Inspectors Found During the System Shutdown

The D.C. Metro was shut down for 29 hours straight earlier this week while inspectors checked for defects in jumper cables, which transmit power between sections of the electrified third rail, along all the track in the system. To its credit, WMATA publicly documented the process.

wmata_cable
Exposed wiring found during an inspection of the D.C. Metro this week. Image: WMATA
false

Stephen Repetski at Greater Greater Washington reports that inspectors found 26 jumper cables needing repair. Exposed wiring in the cables had started a fire on Monday and also caused the fire at L'Enfant Station last year that killed a person via smoke inhalation. The fatality led the feds to take over Metro safety, and at that time system-wide cable inspections were conducted too. Repetski writes:

WMATA replaced 125 cables, and inspections were set up for the cables to be inspected yearly.

[General Manager Paul] Wiedefeld didn't say if any of the 26 cables found Wednesday had been replaced last year, so we don't know if the cables are just one year old and failed recently, or if the issues were missed during routine inspections.

The problem with cable safety can be traced to cuts in staffing for track inspections, Repetski reports:

The Federal Transit Administration issued a scathing 116-page report last summer detailing numerous safety issues that their inspectors found when investigating how WMATA does business.

One of the issues listed in the report is one that claims that the number of people available to do track inspections was cut in half, meaning that each group of two track walkers meant to inspect the rail and nearby equipment includes only one person who is actually inspecting the tracks, fasteners, power equipment, and electrical systems. The other worker, who used to check the tracks as well, is now dedicated to looking out for trains, which could be coming at any time.

The FTA heard from track inspectors themselves who said that they "cannot adequately inspect both running rails and the third rail [where the cables are located]" in the time they have to get the inspections done. A side-effect of this could be that the track personnel skip or gloss over more subtle issues, letting them fester until turning into a full-blown issue.

Elsewhere on the Network today: Bike Portland reports the city will issue anti-dooring decals to Uber and Lyft drivers as well as taxis. And The Urban Edge weighs in on Atlanta's efforts to become less suburban.

Stay in touch

Sign up for our free newsletter

More from Streetsblog New York City

Mamdani Announces Full McGuinness Road Diet, Finishing a Job Halted by Adams

Mayor Mamdani chose the third full day of his tenure to announce that he will complete the full safety redesign of deadly McGuinness Boulevard in Greenpoint — a project that was created under Mayor Bill de Blasio, but watered down by Mayor Adams in a corruption scandal.

January 3, 2026

In With Flynn: New DOT Commissioner Wants To Be ‘Bolder, More Ambitious’

Up close and personal with the 46-year-old native New Yorker and Met fan who wants to carry out Mayor Mamdani's vision for transportation.

January 2, 2026

Mamdani Commissioner Pledges to Hold App Companies Accountable for Road Safety

DCWP Commissioner Sam Levine pledged to crack down on app companies that pressure delivery workers to use e-bikes and cars recklessly.

January 2, 2026

Friday’s Headlines: A Very Streetsblog Inaugural Edition

Mayor Mamdani will govern in prose, thank you very much. Plus other non-inauguration news.

January 2, 2026

Update: New Year, Same Carnage: Two Killed In Separate Hit-and-Runs

It turns out that two hit-and-run drivers killed pedestrians in separate incidents in the early morning hours of New Year's Day.

January 1, 2026

New Year’s Headlines: New Mayor Edition

Happy New Mayor! Plus other news.

January 1, 2026
See all posts