Second Avenue Subway Keeps on Slipping Into the Future

brt_config_3.jpgWhy wait? The optimal BRT configuration on First and Second Avenues would convert multiple traffic lanes to physically separated busways.

Following another revision to the Second Avenue Subway construction timetable, the first phase of the mega-project remains, as ever, about seven or eight years away from completion. Pete Donohue reports in the Daily News:

The Metropolitan Transportation Authorityhas finished an in-depth analysis of the work schedule, budget andpotential hurdles for the long-awaited addition to the system, sourcestold the News.

The conclusion: the official completion date for phase one of theproject should be pushed from June 2015 to December 2016, with possiblefuture delays placing the opening in the summer of 2017, the sourcessaid...

The original schedule for the first phase projected a 2012 completiondate but MTA officials have pushed the date back several times over theyears -- most recently in March 2008.

I'm lucky. I don't have to put up with sardine-style rush-hour commuting on the Lexington Avenue line. But if I did, I'd want relief as soon as possible. Eight years is a long time to ask people to wait, especially when a viable alternative like physically separated Bus Rapid Transit can be provided much sooner, at much less expense. And if experience is any guide, this won't be the last time the Second Avenue Subway gets pushed back, either.

ITDP director Walter Hook said it well in an interview with Streetsblog this February:

I don't know why Japanese and Chinese cities can roll out 10 miles ofnew subway line a year, and the richest city in the world has beentrying and failing to build the Second Avenue Subway since the 1960s.But I've lived in this town a long time, and I am skeptical. Theoptimists are telling us that we will have a Second Avenue Subwaybetween 125th Street and 63rd Street by 2015 and only after we spend $4to $5 billion. So this means we are probably talking about 2018 or2020, and $10 billion. The Second Avenue Subway would be great, it’sneeded, it would have higher demand than almost any other metro line inthe country. At those volumes, metros are often a good investment. Butwill it happen?

The MTA has a huge hole in its next capital program, with billions in funding for core maintenance still unaccounted for. That comes first, no matter what. If our legislative goons in Albany can't muster the will to fund mega-projects, too, we can still expand the system: On the east side of Manhattan, the right BRT configuration would carry almost as many commuters as the Second Avenue Subway, for a fraction of the cost.

Stay in touch

Sign up for our free newsletter

More from Streetsblog New York City

Cyclist: Cop Pulled a Taser During Summons Chase

In a dramatic escalation of the NYPD's criminal crackdown on bike riders, a police officer pulled a stun gun while chasing a cyclist for allegedly running a red light on a regular bike.

May 30, 2025

Albany Pols Seize the Helm(et)

Helmet laws remain controversial — they're the "common-sense" approach pushed by lawmakers who ignore that studies show they don't improve safety.

May 30, 2025

Tisch Reveals Real Reason for Her E-Bike Crackdown: E-Bike Licensing

NYPD Commissioner Jessica Tisch doubles down on her cycling criminalization campaign, saying e-bike licensing is the only other option.

May 30, 2025

Friday’s Headlines: A ‘Critical’ Moment Edition

Cyclists will protest against the NYPD's bike crackdown with a Critical Mass ride to City Hall on Friday. Plus more news.

May 30, 2025

Eyes on the Street: Astoria’s Big Beautiful 31st Avenue Bike Boulevard

Streetsblog paid a visit to New York City's widest on-street protected bike lane ever, which is up and running in Astoria.

May 30, 2025
See all posts