DOT: Pulaski Bridge Bikeway Will Open By End of April
Construction of the Pulaski Bridge bike path is slated to finish at the end of April, according to a DOT spokesperson. As DOT’s bridge division puts together the finishing touches, specifics of the new design are coming to light, including how the bike lane will negotiate the drawbridge section of the Pulaski.
February 22, 2016
Keep L Train Passengers Moving With Great BRT
The news that Sandy-related repairs will require closing one or both directions of the L train under the East River (the “Canarsie Tube”) for one to three years has understandably caused panic among the estimated 230,000 daily passengers who rely on it. Businesses in Williamsburg that count on customers from Manhattan are also concerned about a significant downturn in sales. When the Canarsie Tube was shut down on weekends only last spring, it was bad enough for their bottom line, and this will be much worse.
February 4, 2016
DOT’s Meeker Avenue Safety Plan Is, Well, Meek
DOT unveiled its plan for pedestrian safety improvements along Meeker Avenue in north Brooklyn at last night’s Community Board 1 meeting, but board members and advocates with the “Make Meeker Move” campaign expressed disappointment with DOT's failure to specifically address the safety of bicycling.
January 13, 2016
Lentol: Safety Improvements Coming to Meeker Avenue in 2016
DOT will present safety improvements next month for Meeker Avenue by the BQE in Williamsburg, according to Assembly Member Joe Lentol. The department told Lentol's office it would bring a proposal to Brooklyn Community Board 1 on January 12.
December 16, 2015
Eyes on the Street: Pulaski Bridge Bikeway Rounding Into Form
DOT crews are taking advantage of the frighteningly warmer-than-usual late fall weather to make serious progress on the Pulaski Bridge bikeway.
December 10, 2015
When Will DDC Build the Brooklyn Greenway on Flushing Ave and West Street?
It's been more than three years since NYC DOT announced its full implementation plan for the 14-mile Brooklyn Waterfront Greenway, a series of 23 capital projects that would build out the biking and walking path in high-quality, permanent materials. At the time, DOT said that construction would begin soon on the Flushing Avenue and West Street segments of the greenway, but with 2015 drawing to a close there's still no sign of progress. What gives?
December 1, 2015
Eyes on the Street: Progress on Pulaski Bridge Bikeway
Last week DOT posted photos of construction work on the Pulaski Bridge bikeway on the project's Facebook page. DOT is adding a protected lane that will create more room for people who bike and walk the bridge, which connects Greenpoint and Long Island City over Newtown Creek.
October 15, 2015
Eyes on the Street: Signs That the Pulaski Bikeway Will Really Happen
A reader sends in this shot of the southbound side of the Pulaski Bridge, taken yesterday morning. That was the day NYC DOT said construction would start on the two-way protected bike lane over the bridge, which has been beset by delays until recently.
September 15, 2015
Lentol: Pulaski Bridge Bikeway Construction to Begin September 14
Construction of the Pulaski Bridge protected bike lane is now set to begin in a matter of days, according to Assembly Member Joe Lentol, and could wrap before the end of the year.
September 3, 2015
Citi Bike Expansion Rolling Along — See the Latest Map
Well, that was quick. Just over two weeks after cutting the ribbon on the first of 91 new stations, Citi Bike's expansion into Long Island City, Greenpoint, Williamsburg, and Bedford-Stuyvesant is approaching the finish line.
August 21, 2015